With the motto “Prestige is the future”, on May 4, 2018, Dong Son was honored to be officially awarded the design and construction contract by Star Fashion Co., Ltd. Star” – phase III. Following this event, on July 24, 2018, the Investor continued to choose Dong Son as the contractor to perform the design and construction bidding package of M&E items for the project. This honor once again affirms that the quality of the work done by Dong Son meets the requirements of the investor’s design and construction.
The bidding package for the project “Building a Fashion Star Factory” – Phase 3 includes the main works: (1) Structural and architectural design, (2) Construction for Block 2 Factory, Block 3, Canteen, Garage No. 2 and some other items and (3) Renovation work in the previous phase.
The bidding package started in June 2018 with a completion time of 13 months. Of which 9 months for the design and construction package of new construction items and 4 months for the renovation and construction package of Block 2.
The M&E package includes the design and construction works for (1) the electromechanical system, (2) the fire protection system in accordance with the laws of Vietnam, (3) the smoke extraction system, ( 4) Houses with low-voltage distribution cabinets and generators.
With the determination to complete the project with the best quality, Dong Son will focus all his abilities to carry out the project as committed and satisfy the investor.
Project perspective image:
Some key information of the project:
Total area : 4.5 ha
Implementation time : 13 months
Investor : STAR FASHION COMPANY LIMITED
General Contractor : Dong Son Construction and Trading Joint Stock Company
Location : Lot CN B4, Phu Nghia Industrial Park, Phu Nghia Commune, Chuong My District, Hanoi
Free download Pc Games Crack download for pc Crack for pc Movies review Blog Download Crack for pc Crack Softwares download Download Apps Crack Crack Softwares download